One of your employees is up for promotion.If the promotion is granted,the employee will be reassigned elsewhere causing a problem for you on your project.You can delay the promotion until your project is complete.You should:
A.Support the promotion but work with the employee and the employee's new management to
develop a good transition plan
B.Ask the employee to refuse the promotion until your project is completed
C.Arrange to delay the promotion until the project is completed
D.Tell the employee that it is his responsibility to find a suitable replacement so that the project will
not suffer
SHENSY 1年前 已收到1个回答 举报

老妞儿我爱你 幼苗

共回答了16个问题采纳率:81.3% 举报

A. Support the promotion but work with the employee and the employee's new management to develop a good transition plan
尊重和支持员工的晋升和职业发展,做好项目干系人管理